Cambrian Scaffolding Risk Assesment for Access Scaffolding Project Contractor Document Ref Number: Assessed By Controls 1)Only authorised and competent persons should errect, modify or dismantle scaffolding. 2)Design drawings should be produced for load bearing scaffold and non-standard structures 3)The erection should conform to SG4:15 Regulations 4)Lighting arrangements for a structure on a public highway or right of way should be referred to the local authority. 5)Guard rails and toe boards removed for access should be replaced as soon as possible 6)unused ladder access points should have guard rails and toe-boards fitted. 7)Ties removed for any purpose should be replace immediately or alternative ties fitted. 8)Debris guards/ Debris netting or fans should be considered for very high scaffolds and those scaffolds which are close to public areas. 9)Traffic movement should be restricted around the base of the scaffold 10)Scaffolds should be inspected on handover and a certificate obtained. 11)Supervisors should inspect scaffold prior to exposure to adverse weather conditions or any other alterations. 12)ladders should be boarded, stairs barred and any other precautions taken to prevent trespassers out of hours. PERSONAL PROTECTIVE EQUIPMENT 1)Safety boots, gloves and helmet should be worn. 2) The use of safety nets and safety harnesses may be necessary. Hazards Risk Rating Without Controls With Controls Falls From Height Medium Low Falling Materials Low Low Collapse of structure High Low Other Harm Minor Injuries Low Significant Injuries & Low fatalities Seirious damage to structureof the building vehicles or plant parked in the vicinity of the scaffold Low Other Persons In Danger Scaffolders Other workers using the scaffold Others working in and around the area of the scaffold members of the public other Additional Assesments 3)Manual Handling YESNO 4)Noise (Required if significant tube cutting takes place) YESNO Other Is the task adequately controlled YESNO If NO refer to senior staff for further controls to reduce risks Specific Legislation 5)Management of health and safety at work regulations 1999 (SI 1999/3242) [as amended] 6)Construction (Health & Safety welfare) Regulations BS EN 12811-1 [as amended] 7)Work at height regulations SG4:15 8)Provision and use of work equipment regulations 1998 (SI 1998/2306) [as amended] 9)Manual handling operations regulations 1992 (SI 1992/2793) [as amended] 10)Control of noise at work regulations 2005 (SI 2005/1643) 11)Electricity at work regulations 1989 (SI 1989/635) 12)Personal protective equipment regulations 1992 (SI 1992/2966) [as amended] Other: HSE And Other Guidance 1)HS(G) 150 "Health and Safety in Construction" 2)BS5973 "Code of practice for access and working scaffolds and special scaffold structures in steel" 3)NASC Guidance Note SG4:00 Other: Information Instruction and Training 1)Workers should be made aware that alteration to scaffolds or removal of ties can be only undertaken by competent scaffolders on receipt of specific authority 2)Brick guards and ladders should not be removed. 3)Workers must be instructed not to throw things down form the top of the scaffolding (bombing) 4)Persons erecting any scaffold must be adequately trained and only scaffolders holding C.I.T.B erectors certificate may erect scaffolds higher than 5 metres 5)Supervisors should be fully trained in scaffold inpection 6)Basic training in the form of tool-box talks should be provided to all workers to enable them to identify scaffold components and defects in scaffold Other: Emergency Procedures 1) Standard site emergency procedures should be observed and all persons must know how to raise an alarm in an emergency. Other: Monitoring Procedures 2)Supervisors should check the scaffold regularly and ensure that is is being used in the correct manner. 3)Scaffolds over 2 metres high should be inspected by a competent person before use and every seven days thereafter, the results should be recorded in the form of a scaffold inspection report. 4)Supervisors should take disciplinary action against any worker found undertaking unauthorised scaffold adaptations, alterations or removal of components. 5)Excavations adjacent to scaffolding should be shored to reduce undermining and monitored for signs of undermining. Other: Your Name (required) Your Email (required)